Project Details

  • Program was formally approved by the Cabinet in July 2015
  • AES (Administrative and Executive Sanction) for all four packages has been issued.
  • Independent Review of submitted EIA and RAP completed.
  • Environmental Impact Assessment (EIA) for Phase 1 Roads has been completed and final report submitted by PMC.
  • Resettlement Action Plan (RAP) for Phase 1 Roads has been completed and final report submitted by PMC
  • DPR for Phase 1 Roads has been finalized and final report submitted by the PMC.
  • Egis India Consulting Engineers Private Ltd was awarded the contract for Project Management Consultancy (PMC) for current program on 08 Aug 2014.

Phase I

Sr. No. Project Name Contract Package Length (Km) Date Of Agreement Completion Period
Construction Maintenance
1 Up-gradation and Maintenance of Garautha-Chirgaon Section of SH-42 from Km 118.600 to Km 167.745 NCB No. UPCRNDP/UPG/02/2014 49.145 05-01-2017 24 month 5 years
2 Engineering Procurement and Construction Contract for Up-gradation and Maintenance of Hamirpur-Rath section of SH-42 from Km 2.065 to Km74.255 ICB No. UPCRNDP/UPG/01/2018 72.785 19-06-2019 730 days 1826 days
3 Engineering Procurement and Construction Contract for Up-gradation and Maintenance of Gola-Shahjahanpur section of SH-93 from Km 1.280 to Km 58.580 ICB No. UPCRNDP/UPG/03/2018 57.535 26-06-2019 730 days 1826 days
4 Engineering Procurement and Construction Contract for Up-gradation and Maintenance of Badaun-Bilsi-Bijnaour section of SH-51 from Km 58.400 to Km 137.820 ICB No. UPCRNDP/UPG/04/2018 79.125 05-07-2019 730 days 1826 days
Total Project Length (In Km) 258.590
  • The details of Contract for the above packages are given in tables given below:
Package No. Category From To Length (km) Name of the Contractor Contract Amount (Cr.) Construction Period (Month) Commencement Date
UPG-02 SH-42 Garautha (km118+600) Chirgaon (km167+745) 49.145 M/s NKC Projects Pvt. Ltd. 189.99 24 15-01-2018
UPG-01 SH-42 Hamirpur (km2+065) Rath (km74+255) 72.785 M/s GHV (India) Pvt. Ltd. 262.39 24 25-06-2019
UPG-03 SH-93 Gola (km1+280) Shahjahanpur (km58+580) 57.535 M/s APCO Infratech Pvt. Ltd. 356.90 24 11-11-2019
UPG-04 SH-51 Badaun (km58+400) Bijnaour (km137+820) 79.125 M/s Gawar Construction Ltd. 334.00 24 04-11-2019
Total Length (on-going Contracts) 258.590 km
  • Physical Progress

Package SG GSB WMM DBM BC DLC PQC
Hamirpur Rath 100% 100% 100% 100% 100% 100% 100%
Garautha Chirgaon 100% 100% 100% 100% 100%
Gola Shahjahanpur 100% 100% 100% 100% 100%
Badaun Bilsi 100% 100% 100% 100% 100%
  • Structure Progress

Package Box Culvert Slab Culvert Pipe Culvert Minor Bridge Major Bridge
Hamirpur Rath 100% 100% 100%
Garautha Chirgaon 100% 100% 100% 100%
Gola Shahjahanpur 100% 100% 100% 100%
Badaun Bilsi 100% 100% 100% 100%
  • Financial Progress

Package Expenditure (Crore) Cost (Crore) Percentage Progress
Hamirpur Rath 275.7 275.7 100.0%
Garautha Chirgaon 183.9 183.9 100.0%
Gola Shahjahanpur 356.9 345.01 96.7%
Badaun Bilsi 334.0 332.8 99.6%

Phase II

Package Category Improvement Length (km) Estimated Cost (Cr) Status Remarks
Bansi-Mehndawal-Khalilabad SH-88 2 – Lane +Paved Shoulder 28.870 186.480 DPR Approved. 4 bids received and under evaluation 24.08.22 (Financial) evaluated & sent to WB. NOC received
Baharaich – Gonda- Faizabad SH-30 2 – Lane +Paved Shoulder 59.237 336.380 DPR Approved E Tender floated on 05.08.22 & approval of BD by WB received on 02.08.22
Garh- Syana-Bulandshahar SH-65 4 – Lane +Paved Shoulder 49.674 489.690 DPR Submitted BD Submitted on 09.09.22 to UPPWD
Moradabad-Haridwar-Dehradun SH-49 4 – Lane +Paved Shoulder 36.170 314.480 DPR Approved EIA revised report submitted on 09.09.22 & BD submitted on 12.09.2022
Hamidpur- Kuchesar SH-100 2 – Lane +Paved Shoulder 19.109 106.300 DPR to be submitted as per revised alignment BD Submitted on 08.09.22 to UPPWD
Rath – Garautha (Missing Link) SH-42 2 – Lane +Paved Shoulder 35.882 183.560 DPR Approved. 3 bids received and under evaluation 31.05.22 (Tech.) evaluated & sent to WB for NOC

Note: Data up to April 2023 as per record.