Project Details
- Program was formally approved by the Cabinet in July 2015
- AES (Administrative and Executive Sanction) for all four packages has been issued.
- Independent Review of submitted EIA and RAP completed.
- Environmental Impact Assessment (EIA) for Phase 1 Roads has been completed and final report submitted by PMC.
- Resettlement Action Plan (RAP) for Phase 1 Roads has been completed and final report submitted by PMC
- DPR for Phase 1 Roads has been finalized and final report submitted by the PMC.
- Egis India Consulting Engineers Private Ltd was awarded the contract for Project Management Consultancy (PMC) for current program on 08 Aug 2014.
Phase I
Sr. No. | Project Name | Contract Package | Length (Km) | Date Of Agreement | Completion Period | |
---|---|---|---|---|---|---|
Construction | Maintenance | |||||
1 | Up-gradation and Maintenance of Garautha-Chirgaon Section of SH-42 from Km 118.600 to Km 167.745 | NCB No. UPCRNDP/UPG/02/2014 | 49.145 | 05-01-2017 | 24 month | 5 years |
2 | Engineering Procurement and Construction Contract for Up-gradation and Maintenance of Hamirpur-Rath section of SH-42 from Km 2.065 to Km74.255 | ICB No. UPCRNDP/UPG/01/2018 | 72.785 | 19-06-2019 | 730 days | 1826 days |
3 | Engineering Procurement and Construction Contract for Up-gradation and Maintenance of Gola-Shahjahanpur section of SH-93 from Km 1.280 to Km 58.580 | ICB No. UPCRNDP/UPG/03/2018 | 57.535 | 26-06-2019 | 730 days | 1826 days |
4 | Engineering Procurement and Construction Contract for Up-gradation and Maintenance of Badaun-Bilsi-Bijnaour section of SH-51 from Km 58.400 to Km 137.820 | ICB No. UPCRNDP/UPG/04/2018 | 79.125 | 05-07-2019 | 730 days | 1826 days |
Total Project Length (In Km) | 258.590 |
- The details of Contract for the above packages are given in tables given below:
Package No. | Category | From | To | Length (km) | Name of the Contractor | Contract Amount (Cr.) | Construction Period (Month) | Commencement Date |
---|---|---|---|---|---|---|---|---|
UPG-02 | SH-42 | Garautha (km118+600) | Chirgaon (km167+745) | 49.145 | M/s NKC Projects Pvt. Ltd. | 189.99 | 24 | 15-01-2018 |
UPG-01 | SH-42 | Hamirpur (km2+065) | Rath (km74+255) | 72.785 | M/s GHV (India) Pvt. Ltd. | 262.39 | 24 | 25-06-2019 |
UPG-03 | SH-93 | Gola (km1+280) | Shahjahanpur (km58+580) | 57.535 | M/s APCO Infratech Pvt. Ltd. | 356.90 | 24 | 11-11-2019 |
UPG-04 | SH-51 | Badaun (km58+400) | Bijnaour (km137+820) | 79.125 | M/s Gawar Construction Ltd. | 334.00 | 24 | 04-11-2019 |
Total Length (on-going Contracts) | 258.590 | km |
- Physical Progress
Package | SG | GSB | WMM | DBM | BC | DLC | PQC |
---|---|---|---|---|---|---|---|
Hamirpur Rath | 100% | 100% | 100% | 100% | 100% | 100% | 100% |
Garautha Chirgaon | 100% | 100% | 100% | 100% | 100% | ||
Gola Shahjahanpur | 100% | 100% | 100% | 100% | 100% | ||
Badaun Bilsi | 100% | 100% | 100% | 100% | 100% |
- Structure Progress
Package | Box Culvert | Slab Culvert | Pipe Culvert | Minor Bridge | Major Bridge |
---|---|---|---|---|---|
Hamirpur Rath | 100% | 100% | 100% | ||
Garautha Chirgaon | 100% | 100% | 100% | 100% | |
Gola Shahjahanpur | 100% | 100% | 100% | 100% | |
Badaun Bilsi | 100% | 100% | 100% | 100% |
- Financial Progress
Package | Expenditure (Crore) | Cost (Crore) | Percentage Progress |
---|---|---|---|
Hamirpur Rath | 275.7 | 275.7 | 100.0% |
Garautha Chirgaon | 183.9 | 183.9 | 100.0% |
Gola Shahjahanpur | 356.9 | 345.01 | 96.7% |
Badaun Bilsi | 334.0 | 332.8 | 99.6% |
Phase II
Package | Category | Improvement | Length (km) | Estimated Cost (Cr) | Status | Remarks |
---|---|---|---|---|---|---|
Bansi-Mehndawal-Khalilabad | SH-88 | 2 – Lane +Paved Shoulder | 28.870 | 186.480 | DPR Approved. 4 bids received and under evaluation | 24.08.22 (Financial) evaluated & sent to WB. NOC received |
Baharaich – Gonda- Faizabad | SH-30 | 2 – Lane +Paved Shoulder | 59.237 | 336.380 | DPR Approved | E Tender floated on 05.08.22 & approval of BD by WB received on 02.08.22 |
Garh- Syana-Bulandshahar | SH-65 | 4 – Lane +Paved Shoulder | 49.674 | 489.690 | DPR Submitted | BD Submitted on 09.09.22 to UPPWD |
Moradabad-Haridwar-Dehradun | SH-49 | 4 – Lane +Paved Shoulder | 36.170 | 314.480 | DPR Approved | EIA revised report submitted on 09.09.22 & BD submitted on 12.09.2022 | Hamidpur- Kuchesar | SH-100 | 2 – Lane +Paved Shoulder | 19.109 | 106.300 | DPR to be submitted as per revised alignment | BD Submitted on 08.09.22 to UPPWD | Rath – Garautha (Missing Link) | SH-42 | 2 – Lane +Paved Shoulder | 35.882 | 183.560 | DPR Approved. 3 bids received and under evaluation | 31.05.22 (Tech.) evaluated & sent to WB for NOC |
Note: Data up to April 2023 as per record.